Yanchang Petroleum's Jingbian Gas Storage and Peaking and Supporting LNG Project Launches Sprint Toward “Finale

2024 12/05

Winter is approaching quietly, and the wind is bitterly cold in northern Shaanxi, but the construction site of Jingbian Natural Gas Storage, Peaking and Supporting LNG Project (Jingbian LNG Project) is a hot and energetic scene with high fighting spirit.The builders of Yanchang Petroleum Refining & Chemical Company are launching a final sprint towards the "closing" target at the end of the year with full enthusiasm and firm determination.
Yanchang Petroleum's Jingbian Gas Storage and Peaking and Supporting LNG Project Launches Sprint Toward “Finale
 
 
With the official start of the water filling test of the 2# LNG storage tank, it marks the successful completion of the main construction of the inner tank of Jingbian LNG project and its successful acceptance.At present, the cable insulation test and cable laying work of the whole plant have also been fully completed, which has won valuable time for the subsequent installation and commissioning of electrical instruments.
 
 
 
In order to ensure that the actual volume of work completed can meet the actual operational needs of the production unit, the Project Execution Centre successfully completed the installation of equipment steel structure in early September.As the installation of the basic process pipeline entered the middle and late stages, the Centre and the natural gas company to carry out close communication, inviting the production unit technicians to intervene in advance, the completed project implementation of the "three checks and four" pre-checks, for the discovery of design defects, omissions and other key issues, and timely rectification proposals and the implementation of the design changes, effectively eliminating the unreasonable design, to provide the quality of the project.The unreasonable design provides a solid guarantee for the project quality.According to the person in charge of the process technology group of the project implementation centre, significant progress has been made in the "Three Checks and Four Definitions" inspection work, and the elimination rate has reached about 65%.
 
 
 
In addition, in the pipeline pressure testing, blowing, valve degreasing and other key links, the Project Execution Center and the natural gas company continue to maintain in-depth cooperation, co-organisation and participation in the inspection and acceptance work, through close cooperation between the two sides, effectively shorten the cycle of gas tightness testing and drying treatment before the commissioning, in order to ensure that the process of the commissioning of the first time a solid foundation for the success.